Projects

April 2024 – Pikkala, Finland – load out from the factory to the M/V Living Stone

Project: CVOW (DOMINION) 3x1200mm2 DW C5+4 (2x35km)

2 shifts, total 10 operators, operating with rotating carousel and tensioner. Max speed 12 m/min.

April 2024 – Pikkala, Finland – load out from the factory to the M/V Cable Enterprise

Project: NOIRMOUTIER 3x1000mm2 CABLE 2 (28km)

2 shifts, total 10 operators, operating with rotating carousel and tensioner. Max speed 10 m/min.

April 2024 – Pikkala, Finland – Spooling on the drum

2024 April – Pikkala, Finland. Cable spooling on the drum, using tensioner and carousel operators.

Cable preparation, spooling, operating with tensioners and carousel.

January 2024 – Pikkala, Finland – load out from the factory to the M/V Cable Enterprise

Project: NOIRMOUTIER 3x1000mm2 CABLE 1 + SPARE (28 km + 1.6 km)

3 shifts, total 15 operators, operating with rotating carousel and tensinor. Max speed 10 m/min.

August 2023 – Drammen, Norway – load out from the factory to the Nautilus Maxi & Guard Supplier

2023 August – Drammen, Norway. 2 Projects: REN SKB BKK & REN SKB Beredskapskabel – Morenett / REN 240 / REN 50 .

2 different vessels, 4 Cables from 4 different carousels. Total length around 36km. Max speed 16-18 m/min.

Load out 12h, 1 shift, 5 operators total. Operating with 2 tensioners and a carousel.

July/August 2023 – Pikkala, Finland – Double load out from the Factory to the world largest cable layer M/V Leonardo da Vinci

2023 July/August – Pikkala, Finland. Project Sofia C1 and C2 .

Two different cables, loaded out simultaneously (double loading), using both loading lines. The length of each cable is around 130km. (total 260km)

Load out 24/7, 2 double shifts, 12 h shift, 20 operators total. First line operating with carousel and tensioner and second line operating with tensioner and keeping watch inside a stationary cage.

June 2023 – Drammen, Norway – Load out from the Factory to the Nautilus Maxi

2023 June – Drammen, Norway. Project REN SKB Linja / Vestall, 3x250mm2 / 3x50mm2.

Loadout in one shift – dayshift 12h, 5 operators total. Operating with 2 tensioners and carousel. Max speed 16 m/min.

June 2023 – Drammen, Norway – Cable spooling

2023 June – Drammen, Norway. Cable spooling inside Factory from one carousel to another. Maximum speed 18 m/min.

May 2023 – Load out from the Factory to the M/V Cable Enterprise

2023 May – Project DOLWIN5 SW 1300, Pikkala – Finland. Total 126km.

Loadout 24/7, 2 shifts, 12 h shift, 10 operators total. Operating with tensioner and keeping watch inside a stationary cage.

April 2023 – Load out from the Factory to the M/V Telepaatti

2023 April – Loadout for a domestic submarine cable. From the Factory to the M/V Telepaatti. Pikkala, Finland. 3x95mm2 – 13km.

Dayshift, 12h / shift, 5 operators total. Operating with tensioner and keeping watch inside a stationary cage.

March – April 2023 -Load out from the Factory to the M/V BBC Xingang

2023 March/April – Project Turkish Crossing 1600mm2 cable 9 to 1 – Pikkala, Finland. Loadout from the factory to the M/V BBC XINGANG. 10 cables, total 52km.

Loadout 24/7, 2 shifts, 12 h shift, 10 operators total. Operating with big carousel and tensioner.

March 2023 – Spooling on the drum – Horizontal

2023 March – Project Dominion – Pikkala, Finland. Cable spooling on the drum, using tensioner and carousel operators.

Cable preparation, spooling, operating with tensioners and carousel.

February 2023 – Spooling on-board the M/V Edward Oldendorff

2023 February – Project Vineyard – Blue Offshore, NTG – in Pikkala, Finland (Cable spooling on board the M/V Edward Oldendorff.)

Total 8 persons in one shift. (3 shifts)

Loadout from the Factory to the Vessel.

Pikkala, Finland (Cable load-out from the factory to the vessel using big carousel, tensioners)

1) All preparation and load-out done by us.

2) Load-out 24/7, 12 h shifts, 5 operators in one shift.

Spooling on the Drum – Vertical

Pikkala, Finland (Cable spooling on the drum inside the Factory – using rotating carousel and tensioner operators)