August 2023 – Drammen, Norway – load out from the factory to the Nautilus Maxi & Guard Supplier
2023 August – Drammen, Norway. 2 Projects: REN SKB BKK & REN SKB Beredskapskabel – Morenett / REN 240 / REN 50 .
2 different vessels, 4 Cables from 4 different carousels. Total length around 36km. Max speed 16-18 m/min.
Load out 12h, 1 shift, 5 operators total. Operating with 2 tensioners and a carousel.


July/August 2023 – Pikkala, Finland – Double load out from the Factory to the world largest cable layer M/V Leonardo da Vinci
2023 July/August – Pikkala, Finland. Project Sofia C1 and C2 .
Two different cables, loaded out simultaneously (double loading), using both loading lines. The length of each cable is around 130km. (total 260km)
Load out 24/7, 2 double shifts, 12 h shift, 20 operators total. First line operating with carousel and tensioner and second line operating with tensioner and keeping watch inside a stationary cage.



June 2023 – Drammen, Norway – Load out from the Factory to the Nautilus Maxi
2023 June – Drammen, Norway. Project REN SKB Linja / Vestall, 3x250mm2 / 3x50mm2.
Loadout in one shift – dayshift 12h, 5 operators total. Operating with 2 tensioners and carousel. Max speed 16 m/min.



June 2023 – Drammen, Norway – Cable spooling
2023 June – Drammen, Norway. Cable spooling inside Factory from one carousel to another. Maximum speed 18 m/min.
May 2023 – Load out from the Factory to the M/V Cable Enterprise
2023 May – Project DOLWIN5 SW 1300, Pikkala – Finland. Total 126km.
Loadout 24/7, 2 shifts, 12 h shift, 10 operators total. Operating with tensioner and keeping watch inside a stationary cage.


April 2023 – Load out from the Factory to the M/V Telepaatti
2023 April – Loadout for a domestic submarine cable. From the Factory to the M/V Telepaatti. Pikkala, Finland. 3x95mm2 – 13km.
Dayshift, 12h / shift, 5 operators total. Operating with tensioner and keeping watch inside a stationary cage.


March – April 2023 -Load out from the Factory to the M/V BBC Xingang
2023 March/April – Project Turkish Crossing 1600mm2 cable 9 to 1 – Pikkala, Finland. Loadout from the factory to the M/V BBC XINGANG. 10 cables, total 52km.
Loadout 24/7, 2 shifts, 12 h shift, 10 operators total. Operating with big carousel and tensioner.


March 2023 – Spooling on the drum – Horizontal
2023 March – Project Dominion – Pikkala, Finland. Cable spooling on the drum, using tensioner and carousel operators.
Cable preparation, spooling, operating with tensioners and carousel.


February 2023 – Spooling on-board the M/V Edward Oldendorff
2023 February – Project Vineyard – Blue Offshore, NTG – in Pikkala, Finland (Cable spooling on board the M/V Edward Oldendorff.)
Total 8 persons in one shift. (3 shifts)


Loadout from the Factory to the Vessel.
Pikkala, Finland (Cable load-out from the factory to the vessel using big carousel, tensioners)
1) All preparation and load-out done by us.
2) Load-out 24/7, 12 h shifts, 5 operators in one shift.


Spooling on the Drum – Vertical
Pikkala, Finland (Cable spooling on the drum inside the Factory – using rotating carousel and tensioner operators)
